Apart from the supplied components, you will need at least:

  • 8 bolts, washers, and nuts to secure the clamping plate and the controller unit inside your self-service machine.

  • Installation instructions form the manufacturer of your self-service machine.

Proceed as follows:

        1.  Mount the NFC-reader to the front of the installation panel.

  1. Remove the protective film from the back of the NFC-reader.

  2. Place the stud bolts of the NFC-reader through the holes in the front of the installation panel.

  3. At the back of the installation panel, place the flat side of the clamping plate over the stud bolts.

  4. Secure the NFC-reader using the four supplied M4 washers and nuts to a torque of 0.7 Nm.

  5. Secure the clamping plate to the installation panel.

  6. Remove the protective film from the front of the NFC-reader.


        2.  Secure the controller unit inside the self-service machine near the NFC reader,                 using 4 bolts, washers, and nuts to a torque of 0.7 Nm.


Do not install the control unit inside a chassis that can be removed from the self-service machine.


        3.  Connect the NFC reader to the controller unit.

  1. Connect the SMA (RF) cable to the back of the NFC-reader and to the RF port on the bottom of the control unit.

  2. Connect the RJ45 cable to the back of the NFC-reader and to the COMM port on the bottom of the control unit. Don't use the COM1 port.


The RF port and the COMM port are located next to each other on the bottom of the control unit, and are marked ANT.



        4.  Connect an Ethernet cable between the LAN port on the controller unit and your                 network.



Only connect a regular Ethernet cable to the LAN port.  Using any other type of cable or another port, such as the COM1 RS232 port, might severely damage the device.


        5.  Connect the power cord between the DC IN port on the controller unit and a                     power supply unit in the self-service machine or an external power source.

The controller beeps. After approximately a minute, a green light and an amber light on the LAN port turn on. The terminal starts boarding.


UX410 - Table of Contents



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article